Schedule - Coverage Audit

established project management guidelines processes in the Schedule Knowledge Area, with per-output coverage against the 155 AI_PM requirements. See the Schedule KA detail page for the full list of requirements primarily mapped to this KA.

← Back to Coverage Audit overview · Schedule KA detail →

Plan Schedule Management Covered

Process Group: Planning

Supporting REQs: REQ-FUN-080 REQ-FUN-108 REQ-FUN-114

established project management guidelines OutputStatusSupporting REQsRationale / Gap detail
Schedule Management PlanCoveredREQ-FUN-080Template seeded.
Governance: doc/project-management-guidelines/07_schedule_management_plan.md

Define Activities Covered

Process Group: Planning

Supporting REQs: REQ-FUN-101 REQ-FUN-108

established project management guidelines OutputStatusSupporting REQsRationale / Gap detail
Activity ListCoveredREQ-FUN-101Activity CRUD scoped to project + WBS.
Activity AttributesCoveredREQ-FUN-101
Milestone ListCoveredREQ-FUN-131established project management guidelines distinguishes milestones from activities; AIPM models activities but has no dedicated milestone flag/view. Milestones are tracked in flat-file 08_milestone_list.md. Now covered by REQ-FUN-131 (approved 2026-05-11).
Governance: doc/project-management-guidelines/08_milestone_list.md

Sequence Activities Covered

Process Group: Planning

Supporting REQs: REQ-FUN-102 REQ-FUN-103

established project management guidelines OutputStatusSupporting REQsRationale / Gap detail
Project Schedule Network DiagramsCoveredREQ-FUN-102 REQ-FUN-132Dependency model exists (FS/SS/FF/SF + lag/lead) but only Gantt view renders schedule; no network-diagram visualization. Now covered by REQ-FUN-132 (approved 2026-05-11).

Estimate Activity Durations Covered

Process Group: Planning

Supporting REQs: REQ-FUN-101

established project management guidelines OutputStatusSupporting REQsRationale / Gap detail
Duration EstimatesCoveredREQ-FUN-101 REQ-FUN-133Activity duration is stored but established project management guidelines distinguishes deterministic duration from three-point estimates used in PERT. Three-point estimates not modeled. Now covered by REQ-FUN-133 (approved 2026-05-11).
Basis of EstimatesCoveredREQ-FUN-134established project management guidelines requires recording WHY a duration was estimated as it was (analogous / parametric / expert / three-point). No field exists. Closed by REQ-FUN-134 (approved 2026-05-11).

Develop Schedule Partial

Process Group: Planning

Supporting REQs: REQ-FUN-103 REQ-FUN-104 REQ-NFR-067 REQ-NFR-068

established project management guidelines OutputStatusSupporting REQsRationale / Gap detail
Schedule BaselineCoveredREQ-FUN-104 REQ-NFR-068Versioned, insert-only baseline.
Project Schedule (Gantt)PartialREQ-FUN-106 REQ-NFR-071Read-only Gantt view present. Full drag-and-drop Gantt authoring is intentionally OUT OF SCOPE per scope statement section 4.
Schedule DataCoveredREQ-FUN-103 REQ-FUN-114

Control Schedule Covered

Process Group: Monitoring & Controlling

Supporting REQs: REQ-FUN-105 REQ-FUN-107 REQ-FUN-111 REQ-FUN-112 REQ-FUN-113

established project management guidelines OutputStatusSupporting REQsRationale / Gap detail
Work Performance Information (Schedule)CoveredREQ-FUN-105 REQ-FUN-107 REQ-FUN-111Slippage detection + SPI + forecasted finish.
Schedule ForecastsCoveredREQ-FUN-111
Change RequestsCoveredREQ-FUN-113 REQ-FUN-126Baseline changes require CR (policy); no first-class CR entity. Now covered by REQ-FUN-126 (approved 2026-05-11).