Schedule Management
Plans, develops, manages, and controls the project schedule.
established project management guidelines definition
Project Schedule Management includes the processes required to manage the timely completion of the project. The work products include a schedule management plan, the schedule baseline, a milestone list, and the project schedule itself. Schedule management defines activities, sequences them, estimates durations, develops the integrated schedule, and controls schedule variance.
Processes in this Knowledge Area
Plan Schedule Management
Outputs: schedule management plan.
REQ-FUN-108— Schedule template instantiation seeds activities + dependencies
Define Activities
Outputs: activity list, activity attributes, milestone list.
REQ-FUN-101— Schedule activity CRUD scoped to project and work package
Sequence Activities
Outputs: project schedule network diagrams.
REQ-FUN-102— Activity dependency model (FS/SS/FF/SF + lag/lead in days)
Estimate Activity Durations
Outputs: duration estimates, basis of estimates.
No AI_PM requirements primarily mapped to this process.
Develop Schedule
Outputs: schedule baseline, project schedule, schedule data.
REQ-FUN-103— Critical-path computation triggered on schedule changeREQ-FUN-104— Schedule baseline (versioned, immutable snapshot)REQ-NFR-067— Critical-path computation p95 <= 500 ms at 500 activitiesREQ-NFR-068— Baseline rows insert-only at DB role level (schedule + cost)REQ-NFR-072— Schedule recalculation p95 <= 1 s on activity edit
Control Schedule
Outputs: work performance information, schedule forecasts, change requests.
REQ-FUN-105— Schedule slippage detection vs approved baselineREQ-FUN-107— Schedule report (variance + SPI by project / WBS branch / time window)REQ-FUN-109— Activity status updates via dedicated activity_status_update rowsREQ-FUN-110— Auto-create board item when activity deps are satisfiedREQ-FUN-111— Per-activity forecasted finish date from EV + SPIREQ-FUN-112— Resource over-allocation flag (read-only, no auto-leveling)REQ-FUN-113— Post-baseline schedule changes require approved Change RequestREQ-FUN-114— Schedule export in iCalendar (ICS) and CSV formatsREQ-FUN-106— Read-only Gantt chart view of project scheduleREQ-NFR-071— Gantt view legible at up to 200 activities (desktop)
All requirements primarily mapped to Schedule Management (21)
| ID | Description | Primary Process Group |
|---|---|---|
| REQ-FUN-101 | Schedule activity CRUD scoped to project and work package | Planning |
| REQ-FUN-102 | Activity dependency model with FS/SS/FF/SF and lag/lead | Planning |
| REQ-FUN-103 | Critical-path computation triggered on schedule change | Planning |
| REQ-FUN-104 | Schedule baseline as versioned, immutable snapshot | Planning |
| REQ-FUN-105 | Schedule slippage detection vs approved baseline | Monitoring & Controlling |
| REQ-FUN-106 | Read-only Gantt chart view of project schedule | Executing |
| REQ-FUN-107 | Schedule report with variance and SPI by project, WBS branch, and time window | Monitoring & Controlling |
| REQ-FUN-108 | Schedule template instantiation seeds activities and dependencies | Planning |
| REQ-FUN-109 | Activity status updates via dedicated activity_status_update rows | Executing |
| REQ-FUN-110 | Auto-create board item when activity dependencies are satisfied | Executing |
| REQ-FUN-111 | Per-activity forecasted finish date from EV and SPI | Monitoring & Controlling |
| REQ-FUN-112 | Resource over-allocation flagging (read-only, no automatic leveling) | Monitoring & Controlling |
| REQ-FUN-113 | Post-baseline schedule changes require approved Change Request | Monitoring & Controlling |
| REQ-FUN-114 | Schedule export in iCalendar (ICS) and CSV formats | Executing |
| REQ-FUN-131 | Milestone flag on activity + Milestone List view | Planning |
| REQ-FUN-132 | Project Schedule Network Diagram (PDM) view | Planning |
| REQ-FUN-133 | Three-point duration estimates on activity (PERT) | Planning |
| REQ-NFR-067 | Critical-path computation completes within 500 ms for up to 500 activities | Planning |
| REQ-NFR-068 | Schedule baseline and cost baseline rows are insert-only at DB role level | Planning |
| REQ-NFR-071 | Gantt view renders legibly for projects of up to 200 activities | Executing |
| REQ-NFR-072 | Schedule recalculation on activity edit completes within 1 second | Executing |
Secondary support
Requirements whose primary KA is elsewhere, but which also support Schedule Management.
| ID | Description | Primary KA |
|---|---|---|
| REQ-FUN-118 | EVM rollup (PV, EV, AC, CV, SV, CPI, SPI, EAC, ETC, VAC, TCPI) | Cost Management |