REQ-FUN-120

EAC forecasting by three methods (CPI, CPI*SPI, optimistic)

ID
REQ-FUN-120
Category
Functional Requirements
Status
approved
Priority
P1
Created
2026-05-11T18:34:00.000Z
Approved
2026-05-11T18:37:00.000Z
Updated
2026-05-11T18:37:00.000Z

What

For each project, system SHALL compute Estimate At Completion using three established_guidelines_standard methods: EAC_cpi = BAC / CPI (typical performance continues), EAC_cpi_spi = AC + (BAC - EV) / (CPI * SPI) (both cost and schedule performance continue), and EAC_optimistic = AC + (BAC - EV) (remaining work as originally budgeted). All three are returned in the EVM response.

Why

established project management guidelines Control Costs documents these three forecasting methods; different stakeholders trust different assumptions. Showing all three avoids hiding uncertainty.

How

Extends the REQ-FUN-118 response with eac_cpi, eac_cpi_spi, eac_optimistic fields. Web UI defaults to showing eac_cpi but exposes the other two on hover/expand.

Done when

All three EAC values computed; reference-textbook example reproduces the documented values; UI defaults to eac_cpi with the others accessible.

Out of scope

Custom user-supplied EAC formulas.

established project management guidelines Mapping

Primary Knowledge Area
Cost Management
Secondary KAs
none
Primary Process Group
Monitoring & Controlling
established project management guidelines Deliverable
Status Report

EAC forecasting - established project management guidelines Control Costs forecast output.